| Lead Time: |
Start Time: 07/09/07 End Time: 06/10/07 |
|---|---|
| APQP: | Not Required |
| Part Spec: | PP |
| Mould Flow: | Required |
| Tool: | 4 imp hardened to 48-52 Rockwell C |
| 3D Model: | Not Required |
| Summary: |
Not a particularly tricky tool but we included this in our studies because we completed this 4 imp construction part in 5 weeks including a tool drawing and product design. It was required to finish off a housing project. The customer arrived to view sampling, they approved the part there and then, and then we ran the order off without a hitch. |