Case Study 4

Lead Time: Start Time: 13/02/06
End Time: 07/04/06
APQP: Not Required
Part Spec: Polyprop
Mould Flow: Required
Tool: 1 IMP Fully Hardened to Rockwell 43C
3D Model: Required
Summary:

After modelling the part for the customer in just 8 hours a few minor design changes were required before we could progress to tooling.


This part for the roofing market was far from difficult, very straightforward in fact with no close moulding tolerances either.


It was completed in just under 8 weeks, approved first time and underwent its first production run.

Video:
Get the Flash Player to see this player.

ISO9001 Registered TS16949 Registered BRC Approved Project part-financed by the European Union. European regional developement fund.